Basement finish calculator
Rigid foam on the foundation, 2x4 walls in front of it, drywall, LVP over insulated subfloor, trim, lighting and outlets: every material line a finished basement takes, from five numbers.
An estimate of the materials a job takes, worked out in your browser: check it against the job, and against your local code where it matters. Nothing you type leaves this page.
Put in the job's numbers and choices, and the list below follows them.
What it takes
Worked out for Finished area 1,000 sq ft, Ceiling height 8 ft, Foundation wall 130 ft, Partition walls 60 ft, Interior doors 2 each, Sound-insulated walls 40 ft, Mechanical room enclosure 32 ft, Climate zone: Zone 4–5, Foam board: XPS, Ceiling joists: 16 in apart, Sound batts in partitions: Yes, LVP onto the stair landing: Yes.
Air sealing and rim joist
- Closed-cell spray foam kit 1 kit Foundation wall 130 ft, one per 250: 0.52 kit; rounded up to whole kit: 1. Froth-Pak 620 or equal, for the rim joist band.
- Pro foam cans, 24 oz 8 can Finished area 1,000 sq ft, one per 125: 8 can. For penetrations, plate gaps and small voids.
- Foam dispensing gun 1 each A fixed 1: 1 each.
- Fire block foam 4 can Partition walls 60 ft, one per 15: 4 can. At penetrations through a fire separation; check local code.
Rigid foam on the foundation walls
- 2 in XPS rigid foam board, 4x8 36 sheet Foundation wall area 1,040 sq ft at 32 a sheet: 32.5 sheet; plus 10% waste: 35.75; rounded up to whole sheet: 36. Not polyiso below grade.
- Foam-safe construction adhesive 26 tube Foundation wall area 1,040 sq ft, one per 40: 26 tube. Solvent adhesives melt foam.
- Foam seam tape, 3 in x 180 ft 3 roll Foundation wall area 1,040 sq ft, one per 400: 2.6 roll; rounded up to whole roll: 3. Every seam and edge: it is the air barrier.
- Utility knife blades, bulk 1 pack A fixed 1: 1 pack.
Left out: 3 in XPS rigid foam board, 4x8 (only when Climate zone is Zone 6 and colder).
Framing
- 2x4x8 SPF stud 195 each Wall length 190 ft + (Interior doors 2 each × 2.5): 195 each. About one per foot of wall covers studs at 24 in, the doubled top plate, blocking and corners; two and a half more frame each door.
- 2x4x8 pressure treated 27 each Wall length 190 ft at 8 a piece: 23.75 each; plus 10% waste: 26.13; rounded up to whole each: 27. Bottom plates, on the concrete.
- Sill seal foam gasket, 3-1/2 in x 50 ft 4 roll Wall length 190 ft at 50 a roll: 3.8 roll; rounded up to whole roll: 4.
- 3 in framing screws, 5 lb 5 box Wall length 190 ft, one per 40: 4.75 box; rounded up to whole box: 5.
- Tapcon concrete screws, 100 ct 2 box Wall length 190 ft, one per 100: 1.9 box; rounded up to whole box: 2. Bottom plate to slab, about 24 in apart.
- Masonry drill bit 1 each A fixed 1: 1 each.
- Construction adhesive, 28 oz 6 tube Wall length 190 ft, one per 32: 5.94 tube; rounded up to whole tube: 6.
Batt insulation
- R-13 unfaced batts, 23 x 93 in 14 bag Foundation wall area 1,040 sq ft at 77.5 a bag: 13.42 bag; rounded up to whole bag: 14. Unfaced: the foam is the vapor control.
- R-13 sound batts 5 bag Sound-insulated walls 40 ft × Ceiling height 8 ft at 77.5 a bag: 4.13 bag; rounded up to whole bag: 5.
Drywall and finishing
- 1/2 in ultralight drywall, 4x8 69 sheet Wall area 2,000 sq ft at 32 a sheet: 62.5 sheet; plus 10% waste: 68.75; rounded up to whole sheet: 69.
- 1/2 in ultralight drywall, 4x8 35 sheet Finished area 1,000 sq ft at 32 a sheet: 31.25 sheet; plus 10% waste: 34.38; rounded up to whole sheet: 35. Joists 24 in apart take 5/8 in on the ceiling.
- 5/8 in Type X drywall, 4x8 8 sheet Mechanical room enclosure 32 ft × Ceiling height 8 ft at 32 a sheet: 8 sheet. Mechanical room enclosure; check local code.
- Drywall screws 1-1/4 in, 25 lb 1 box Drywall area 3,000 sq ft, one per 3200: 0.94 box; rounded up to whole box: 1.
- Drywall screws 1-5/8 in, 5 lb 1 box A fixed 1: 1 box.
- All-purpose joint compound, 4.5 gal 7 bucket Drywall area 3,000 sq ft, one per 450: 6.67 bucket; rounded up to whole bucket: 7. Three coats.
- Paper joint tape, 500 ft 3 roll Drywall area 3,000 sq ft, one per 1000: 3 roll.
- Metal corner bead, 8 ft 14 each Wall length 190 ft, one per 14: 13.57 each; rounded up to whole each: 14.
- Sanding sponges, pole sander and screens 1 lot A fixed 1: 1 lot.
- Mud pan and knives 1 set A fixed 1: 1 set.
- Access panel, 14 x 14 in 2 each A fixed 2: 2 each. Over any valve, cleanout or damper.
- Acoustic caulk 4 tube Wall length 190 ft, one per 50: 3.8 tube; rounded up to whole tube: 4.
Paint
- PVA drywall primer, 5 gal 2 bucket Drywall area 3,000 sq ft × 1 coat at 1500 a bucket: 2 bucket.
- Interior wall paint, eggshell, 5 gal 2 bucket Wall area 2,000 sq ft × 2 coats at 2000 a bucket: 2 bucket.
- Ceiling paint, flat, 5 gal 1 bucket Finished area 1,000 sq ft × 2 coats at 2000 a bucket: 1 bucket.
- Rollers, trays, brushes, tape and plastic 1 lot A fixed 1: 1 lot.
Flooring
- Insulated subfloor panel, 2x2 300 panel Finished area 1,000 sq ft at 4 a panel: 250 panel; plus 20% waste: 300.
- Perimeter spacer kit 2 kit Foundation wall 130 ft, one per 65: 2 kit.
- Self-leveling compound 6 bag Finished area 1,000 sq ft, one per 170: 5.88 bag; rounded up to whole bag: 6. Check the slab with a straightedge first.
- LVP flooring 1,100 sq ft Finished area 1,000 sq ft: 1,000 sq ft; plus 10% waste: 1,100.
- T-molding transition strip 4 each Interior doors 2 each × 2: 4 each.
- Stair nose trim 1 each A fixed 1: 1 each.
Trim and doors
- Primed baseboard, 3-1/4 in x 16 ft 16 each Baseboard length 244 ft at 16 a piece: 15.25 each; rounded up to whole each: 16.
- Prehung interior door, 32 in 2 each Interior doors 2 each: 2 each.
- Door casing set 2 set Interior doors 2 each: 2 set.
- Finish nails, 16 ga and 18 ga brad 1 lot A fixed 1: 1 lot.
- Paintable caulk 8 tube Baseboard length 244 ft, one per 32: 7.63 tube; rounded up to whole tube: 8.
- Door knob or privacy set 2 each Interior doors 2 each: 2 each.
Electrical
- 20A dual-function AFCI/GFCI breaker 3 each Receptacle circuits 2 each + Lighting circuits 1 each: 3 each. Match the panel brand.
- 12-2 NM-B wire, 250 ft 3 roll Receptacle circuits 2 each + Lighting circuits 1 each: 3 roll.
- 12-3 NM-B wire, 50 ft 1 roll Three-way switches 4 each, one per 4: 1 roll. Three-way switch legs.
- New-work box, 20 cu in 31 each (Receptacles 21 each + Single-pole switches 6 each) + Three-way switches 4 each: 31 each.
- 4 in square box and mud ring 8 each Recessed lights 32 each, one per 4: 8 each.
- 20A tamper-resistant receptacle 21 each Receptacles 21 each: 21 each. Tamper-resistant; check local code for spacing.
- Single-pole switch 6 each Single-pole switches 6 each: 6 each.
- Three-way switch 4 each Three-way switches 4 each: 4 each.
- LED-rated dimmer 4 each Three-way switches 4 each: 4 each.
- Wall plate 31 each (Receptacles 21 each + Single-pole switches 6 each) + Three-way switches 4 each: 31 each.
- 6 in canless LED recessed light, 4-pack 8 pack Recessed lights 32 each at 4 a pack: 8 pack.
- Wire connectors 2 pack A fixed 2: 2 pack.
- Cable staples, 1000 ct 1 box A fixed 1: 1 box.
- Steel nail plate 50 each Wall length 190 ft, one per 4: 47.5 each; plus 5% waste: 49.88; rounded up to whole each: 50. Wherever wire runs near a stud face; check local code.
- Hardwired interconnected smoke and CO alarm 3 each Finished area 1,000 sq ft, one per 400: 2.5 each; rounded up to whole each: 3. Check local code for where alarms go.
- Panel labels and electrical odds and ends 1 lot A fixed 1: 1 lot.
Mechanical and odds and ends
- Supply register and boot 6 each Finished area 1,000 sq ft, one per 170: 5.88 each; rounded up to whole each: 6.
- Duct take-offs, collars, dampers and foil tape 1 lot A fixed 1: 1 lot.
- Return air grille 2 each Finished area 1,000 sq ft, one per 500: 2 each.
- Dehumidifier with condensate pump, 50 pt 1 each A fixed 1: 1 each.
- Fasteners, shims, blades and hardware 1 lot A fixed 1: 1 lot.
Labor
- Drywall hanging and finishing 3,000 sq ft Drywall area 3,000 sq ft: 3,000 sq ft.
- Base trim 244 ft Baseboard length 244 ft: 244 ft.
Contingency
- Allowance 10% allowance 10% of the run's materials cost. Waste, re-buys and what the walls hide.
What it leaves out
- Egress window or window well
- Bathroom rough-in, fixtures or any plumbing
- Permits and inspection fees
- HVAC load calculation
- Foundation crack repair, drain tile or sump work
The same calculator in SMG Tools
In SMG Tools this calculator fills its numbers from the client's site measurements, prices every line from your own Price Book, checks the margin against your target, and carries the lines onto the proposal, the job's plan and the purchase order. It is one of the ready-made calculators SMG Tools sets up for remodeling, and calculators are on every plan.